Saxony approves large battery storage facility near Freiberg

On 26 November 2026, the Saxony Regional Directorate granted planning permission for a battery storage facility in Wegefarth. The facility is intended to store electricity temporarily and later feed it back into the grid.

The Saxony State Directorate approved the construction of a large battery storage facility in Wegefarth at Freiberg approved. Planning permission has now been granted for the proposed facility in the municipality of Oberschöna according to the authority. The storage facility is expected to have a power output of up to 700 megawatts and a capacity of around 2,800 megawatt-hours. The project developer is CI V Gigastar ProjectCo GmbH.

The facility is intended to store electricity when it is abundant and feed it back into the grid when needed. The Regional Directorate expects it to help stabilise the electricity grid. Whether, and to what extent, the facility will also affect electricity prices in future depends, among other things, on when it is charged and discharged. The approval alone does not yet tell us anything about that.

Power output and capacity describe different characteristics of the facility: the planned 700 megawatts indicate how much electricity it can take in or feed out at any one time. The 2,800 megawatt-hours refer to the amount of energy stored. In theory, this would be enough to supply power at full output for four hours; actual operating conditions and losses are not taken into account.

According to the Regional Directorate, the planned amount of energy could, in theory, meet the average daily needs of around 250,000 to 300,000 households. This is an indication of scale, not a promise that the facility will supply these households directly or continuously. Béla Bélafi, President of the Regional Directorate, described a project of this scale as unprecedented in Saxony.

Two separate units are planned on a site covering 11.06 hectares. The first construction phase is to have an output of 500 megawatts, with a further 200 megawatts in the second phase. A new substation and an underground cable will connect the facility to the existing Freiberg Nord substation and the transmission grid. The storage facility is therefore not intended for individual households, but as part of the wider regional grid infrastructure.

According to the authority, the approval process involved around 100 objections, including 66 from individuals and two from nature conservation organisations. These were considered as part of the planning approval process. The decision is due to be available on the planning authority’s website for two weeks from 30 November 2026. At the time of the announcement, it was not yet clear whether legal action would be taken against it.

Local effects are also part of the plans. Earth banks planted with native shrubs are intended to screen the facility from the surrounding area. According to the Regional Directorate, measures involving demolition and the removal of hard surfacing are planned to compensate for impacts on nature and the landscape in Brand-Erbisdorf .

The project is one of a series of large-scale storage plans in Germany. In Klostermansfeld in Saxony-Anhalt, construction began in July 2026 on a park with an output of one gigawatt. For Wegefarth, the granting of planning permission is initially a decisive step in the planning process. Construction and subsequent operation remain dependent on the project developer’s further implementation of the plans.

Editor: Mira Cadena (Article created with AI assistance).