The Saxony State Directorate approved the construction of a large battery storage facility in Central Saxony The facility is to be built in Wegefarth, a district of the municipality of Oberschöna, and will have a capacity of up to 700 megawatts. According to the authority, the approved plans mean that planning permission has been granted. The project developer is CI V Gigastar ProjectCo GmbH.
The facility is planned to have a storage capacity of around 2,800 megawatt-hours. While capacity in megawatts indicates how much electricity the facility can take in or supply at any one time, storage capacity describes the amount of energy stored. At full output of 700 megawatts, this would equate to four hours of operation. The actual operating time depends, among other things, on the output at which the storage facility is used and how fully charged it is.
The battery is intended to store electricity when it is plentiful and feed it back into the grid at a later time. The Saxon Directorate expects the storage facility to help stabilise the electricity grid and contribute to a more reliable supply. The approval alone does not make it possible to determine whether, or to what extent, this will affect electricity prices.
The project is planned in two construction stages across a total area of 11.06 hectares. The first stage is to comprise a 500-megawatt block, followed by a further 200-megawatt block. Both are planned as independent operating units. The connection to the transmission grid is to be made via a new substation and an underground cable to the existing Freiberg North substation .
The Saxon Directorate considers the facility to be unprecedented in Saxony in terms of its size. Directorate President Béla Bélafi said the procedure had presented specialists with particular challenges. According to his calculation, the planned storage capacity is equivalent to the average daily electricity demand of around 250,000 to 300,000 households. This is a mathematical comparison, not a promise that the battery will supply these households directly.
At the planning approval procedure According to the authorities, around 100 objections were submitted. Of these, 66 came from private individuals and two from nature conservation organisations. The objections were considered as part of the procedure. The Saxon Directorate’s statement does not specify the concerns raised or how each was dealt with.
Earth banks planted with native shrubs are planned along the edges of the facility to screen it from view. The impact on nature and the landscape is to be offset by demolition and the removal of sealed surfaces in Brand-Erbisdorf The planning approval decision is to be available on the Saxon Directorate’s website for two weeks from 30 November 2026. The approval provides the basis for the project; the statement did not give a date for construction to begin or for the facility to enter service. The possibility of legal action against the decision should also be distinguished from the approval that has been granted.