In Greifswald will be Anklamer Straße closed to outbound traffic from 16 November 2026. According to the city, the restriction is expected to last until 20 November. It is to allow preparatory work for the installation of a new drinking water pipe. City buses will also have to take a different route.
The closure affects the stretch between the junction with Hans-Beimler-Straße and Walther-Rathenau-Straße, as well as Karl-Liebknecht-Ring. Anklamer Straße will remain open towards the city centre, with traffic operating one way. Drivers heading out of the city towards Anklam should follow the signposted diversion.
According to Greifswald Municipal Utilities According to Greifswald municipal utilities, the additional restrictions will begin at around 8 am on 16 November. The work will prepare for and secure exploratory excavations on drinking water supply pipes. On 4 November, the city said that the excavations were necessary ahead of a planned pipe replacement. The current road closure is therefore part of the preparations and does not mean the pipe project has been completed.
According to notices from the city and the municipal utilities, routes for passengers on services 21 and 22 towards Schönwaldewill change. They will run via Hans-Beimler-Straße and Karl-Krull-Straße to Makarenkostraße bus stop. Südstadt and Karl-Krull-Straße stops will continue to be served. According to the municipal utilities, service 20 will run as usual towards the central bus station.
The municipal utilities expect the drinking water supply to remain fully operational throughout the works. The city gives 20 November as the expected end date for the traffic restrictions; the notices available do not give a later date for the installation of the new pipe.
From 9 to 13 November, a half-width closure was scheduled near Johann-Stelling-Straße. Temporary traffic lights were to control traffic in both directions. During this first phase, it was also not possible to enter or leave Johann-Stelling-Straße. The newly announced arrangement differs: direct outbound traffic will be entirely suspended on the affected stretch, while the opposite direction remains open.
The roadworks coincide with another project on Greifswald’s road network. Since 11 November, the municipal utilities have been building a local electricity substation on Gützkower Landstraße . According to the company, traffic there is being guided past the works using temporary traffic lights. This work is expected to continue until 4 December.
The municipal utilities are responsible for both projects; the city provides information about local traffic restrictions. While the work on Anklamer Straße concerns preparations for a drinking water pipe, the site on Gützkower Landstraße is for the electricity supply. Their schedules and traffic arrangements should therefore be considered separately.