The Gera Central Station has been open to train services again since 16 November 2026. The second full closure in a matter of weeks ended as scheduled at 4 am, according to MDR. However, passengers travelling on the route to Jena should still expect disruption: buses are replacing trains there from 8 am to 4 pm, Monday to Saturday, until 27 November.
The Deutsche Bahn had closed the station completely for track work from the evening of 13 November until the early hours of 16 November. According to infrastructure company DB InfraGO several neighbouring routes were also affected, including services towards Leipzig, Weida, Jena and Erfurt. Buses had been laid on for cancelled trains. The station’s reopening brought this extensive closure to an end, but did not mark the end of all construction work in the region.
According to MDR, trees are being felled and slopes secured between Gera and Jena. The service notice from Erfurter Bahn confirms the recurring daytime closure of the line and replacement bus services until 27 November. Buses cannot serve some replacement stops. According to the transport operator, these include the replacement stop for Papiermühle in Bollberg, because a road is closed in Quirla .
Passengers therefore need to distinguish between the lifting of the full closure at the main station and the continuing work on the route to Jena. Anyone travelling on this route will still need to follow the replacement timetable during the stated daytime hours. Deutsche Bahn directs passengers to its journey planner and station notices for updates and details of replacement services.
Work in Gera had already caused a longer interruption in the autumn. After a ten-day full closure, the main station reopened to train services on 19 October. At the time, work was also carried out on electronic interlockings in Gera and Wolfsgefärth . The November closure was another phase of the track work that has been under way since September.
According to MDR, sleepers were replaced on 15 tracks and a set of points was renewed. Deutsche Bahn said the work at the station and on the route to Jena was carried out separately because it was not possible to undertake an unlimited number of measures safely at the same time. For passengers, this meant that the two station closures were followed by further disruption on a single route.
The distinction also matters when planning connections: during the full closure, replacement buses served several directions. The route to Jena is now subject to a time-limited recurring closure. The relevant timetable shows which services are running in each case and where replacement buses stop.