Latest

Bridge demolition keeps the A99 near Munich closed on 22 November

The eastern Munich ring road will remain closed on 22 November 2026 for the demolition of a damaged bridge near Haar. It is scheduled to reopen the following morning.

a damaged bridge near Haar Haar will disrupt traffic on Munich’s eastern ring road on 22 November 2026. The A99 is closed between the München-Ost and München-Süd interchanges in both directions. According to plans by Autobahn GmbH of the Federal Government the road is due to reopen at 5 am on 23 November. Work began on the evening of 20 November.

The bridge being demolished carried the B 304 over the motorway at the Haar junction. According to Autobahn GmbH, the structure, built in 1973, is so badly damaged that it can no longer be repaired. A new bridge is to be built in its place. Meanwhile, traffic on the B-road is being routed over a temporary bridge; according to the town of Haar, it will remain open during the demolition.

The closure affects an important route in the wider Municharea. The eastern section of the motorway ring will temporarily be unavailable for through journeys between the two interchanges. According to Autobahn GmbH, some slip roads within the section will remain open, but will lead away from the closed area. The restrictions therefore differ for traffic on the A99 and traffic on the intersecting B-road.

Autobahn GmbH expects journeys to be diverted onto roads in Munich and the surrounding area. The town of Haar has also warned that journey times to the trade fair and the airport could be longer. Whether and where traffic jams occur will depend on actual traffic volumes. The predicted disruption is a forecast, not an account of the entire closure weekend.

For lorries, large-scale diversion routes have been signposted, according to information published by the municipality of Zorneding The notice does not specify a recommended diversion for cars. Autobahn GmbH is asking people to avoid non-essential car journeys during the closure and to use buses and trains where possible. The municipality of Grasbrunn notes that there is no single suitable diversion route capable of accommodating the A99’s large traffic volumes.

The demolition also requires a full closure for safety reasons: according to the municipality of Grasbrunn, the damage means it cannot be ruled out that the remaining parts of the bridge could lose their structural stability if it were only partially demolished. Before the demolition work itself began, the motorway carriageway was covered with protective sheeting and a layer of gravel to minimise the risk of falling debris damaging it.

The road’s reopening on 23 November is conditional on the demolition and necessary follow-up work being completed. The replacement bridge will take longer: according to information published by Zorneding, it is due to be completed by the end of 2028. Until then, the temporary bridge is to carry traffic over the motorway.