In Bad Schandau saw the third of four launching operations for a temporary bridge over the railway tracks begin. Saxony’s Ministry of Infrastructure said the first two stages had been completed on schedule. The temporary crossing on Federal Highway 172 is intended to carry traffic while the existing bridge is demolished and replaced.
The steel superstructure is being assembled in sections on the Bad Schandau side and pushed towards Königstein over the railway tracks. According to the ministry, the structure is 147 metres long, weighs around 630 tonnes and spans seven tracks. For the work, Deutsche Bahn arranges track closures in advance. The final launch is scheduled for 30 November 2026; the superstructure is then expected to reach the abutment on the Königstein side.
Saxony’s Minister for Infrastructure Regina Kraushaar and Mayor Thomas Kunack visited the construction site on 23 November to learn about the progress of the project. The ministry expects the temporary bridge to open in the first quarter of 2027. Before then, the superstructure must be moved into its final position after the last launching operation. The connections to the federal highway and work on the railway infrastructure also remain to be completed, according to the ministry.
The replacement is necessary because the existing road bridge over the railway tracks is in poor structural condition. Since 21 October 2025, traffic has been restricted to one lane and controlled by traffic lights for safety reasons. According to the city, this followed a special inspection; a monitoring system is keeping the structure under observation. Pedestrians can continue to use the pavements, while cyclists must walk their bikes.
The restriction affects the railway crossing and not the neighbouring Elbe Bridge. Both form part of a series of bridges along the federal highway. This distinction matters for traffic arrangements: the city points out that the Elbe Bridge is not affected by the single-lane restriction at the railway tracks.
Under the state’s plans, the old railway bridge is to be taken out of service and dismantled in 2027, once the temporary bridge is complete. A new bridge is then to be built on the same site. According to the ministry, the demolition plans are complete; a company is expected to be commissioned to carry out the work by mid-2027. Planning for the new bridge is still under way.
For the region, therefore, relief depends on more than simply pushing the steel superstructure into place. The temporary bridge can fulfil its function only once the remaining connection work is complete and it opens to traffic as planned. It is also intended to allow road traffic to pass the construction site during the subsequent demolition and rebuilding. Until it opens, the existing traffic-light system remains in force.